Solarpark Tiste
The Tiste solar park, which is under construction, is located near the former farmstead “Herwigshof.” Tiste is a neighboring municipality to our company located in Heidenau.
Project description
The solar park spans approximately 50 hectares of former agricultural land and is located south of an EVB railway line.
A project-specific building plan was created with five designated “Solar” zones. Building permits were granted in August 2024.
The park is currently under construction.
Are you considering a solar park for your land or community?
Use our contact form for a non-binding inquiry – we look forward to hearing from you!
Facts and Figures
Location | Tiste, Lower Saxony, Germany |
Surface | approx. 50 ha |
Installed capacity | 46,000 kWp |
Commissioning | August 2025 (planned) |
Specific annual yield | approx. 1,049 kWh/kWp |
Feed-in tariff | partial subsidy according to EEG |
Grid operator | EWE Netz GmbH |